James Creek had an issue with the access to the creek being blocked by gravel/sand at the mouth of the Creek. We removed the blocked entrance and then added some boulders and rocks along the corner bend to help scour the mouth open so that migrating salmon and trout will be able to access the creek.
Landowner of James Creek donated $2,000 worth of large boulders from his property for the stream restoration.
Project work included:
• 65ft (19.8m) x 32ft (9.7m) = 2080 ft2 (634m2) of restored/protected fish habitat
• Boulder cluster (6 boulders)
• Dredged mouth of the Creek
• Installation of 15 yards of boulders
Landowner of James Creek donated $2,000 worth of large boulders from his property for the stream restoration.